Day sheet

Oak & Lime Exteriors

Q-024 · Alex Morgan

24 Orchard Road, Winchester

Sample. For the crew.

Access and scaffold

  • 12 m of scaffold. No extra weeks typed.
  • Access and scaffold: side gate.

Colour and finish

Ivory · Scraped

Start week

Week 2. Scaffold up.

Notes on the photo

  • 1.Check this patch on site
  • 2.dish to be removed and refitted, or worked around

Order list

ItemOrderFrom the quote
Monocouche, 25 kg bagsOrder38 bagsFrom the quote34 m², plus 10% waste: about 1 m² a 25 kg bag at 15 mm finished, roughly 25 kg a square metre
Primer, 20 L drumsOrder1 drumFrom the quote34 m², plus 10% waste: about 100 m² of one coat a 20 L drum
MeshOrderNone on this quoteFrom the quoteMesh is not on this quote.
PVC-u corner, stop and bell beadOrder11 lengthsFrom the quote24 m, plus 10% waste.
Scaffold weeksOrderNo extra weeks typedFrom the quoteThe scaffold run is on the quote. No extra weeks were typed.
SkipOrder1 skipFrom the quoteCounted from the quote.

Before you leave

  • Beads and stop ends.
  • Curing time noted.
  • No guarantee typed on this quote.
  • Photos of the finished work.

Check the day before you apply. Render isn't applied below 5°C, in frost or in rain. Guidance only. Do not apply through-coloured render onto a frozen wall. One maker prints 5 °C to 35 °C and at least 48 hours of cover from rain and frost. Another prints 5 °C to 30 °C and says do not apply if frost is forecast within 24 hours. The tub on this job sets the days.